What's the timeline for the crude vegetable oil refining project?

Industry News / Chat on line / Give me a price / Date:2024-03-27

To construct a crude vegetable oil refining project, many preparatory works need to be finished, such as conducting project feasibility analysis, preparing funds, raw materials and plant land, purchasing crude vegetable oil refining machines. According to DOING's 10+ years crude vegetable oil refining project installation experience, it takes at least half of a year to finish the construction of the entire crude vegetable oil refining project.

This article will show you the detailed timeline, including preparation cycle, machine manufacture cycle, delivery cycle and installation cycle.

1. Fundamental preparatory work cycle: uncontrollable

The preparatory works needed to finish in the fundamental preparatory work cycle include conducting project feasibility analysis, raising funds, collecting crude vegetable oil, selecting land sites and preparing plant land, purchasing crude vegetable oil refining machines. The real timeline in this cycle subject to the actual execution situation of investors.

DOING crude vegetable oil refining machineDOING crude vegetable oil refining machine

2. crude vegetable oil refining machine manufacture cycle: about 2-3 months

The machine manufacture cycle is influenced by two factors: one is the processing capacity of crude vegetable oil refining machine, and the other is the company's order arrangement. And it takes about 2-3 months to finish the machine manufacture.

Henan DOING company has our own factory. After receiving the advance payment and signing the contract, we will arrange production and shipment as soon as possible. If you do not have your own freight forwarder, we can also find a suitable freight forwarder for you. If you are in Africa, we can prioritize shipment from our Nigerian branch for you to reduce the freight costs.

3. crude vegetable oil refining machine delivery cycle: about 2 months

Commonly speaking, the machine delivery cycle is influenced by transportation distance and transportation company situation, it takes less time to delivery machine by direct shipment than transshipment. And the detailed cycle is about 2 months.

The shippment of DOING crude vegetable oil refining machineThe shippment of DOING crude vegetable oil refining machine

4. crude vegetable oil refining machine installation cycle: about 2-3 months

The works needed to be executed in this cycle consist of machine installation, machine commissioning, trial run, workers training, etc. The machine installation cycle mainly varies from the machine processing capacity, worker cooperation, work efficiency, crude vegetable oil refining plant construction and installation tools completeness, etc. In general, it takes about 2-3 months to finish the installation cycle.

HENAN DOING provides free installation and operation training, which can be in the form of online training or on-site training, and we can adjust it according to customer needs.

The above timeline is based on large scale (≥30TPD) continuous crude vegetable oil refining project. If you choose a small batch type and medium-sized semi-countinous type crude vegetable oil refining project, the timeline of the entire crude vegetable oil refining project will be shorter.

DOING crude vegetable oil refining machinesDOING crude vegetable oil refining machines

Henan DOING Company has helped clients from more than 30 countries and regions to install the crude vegetable oil refining project. According to clients' feedback, they feel satisfied with our high quality crude vegetable oil refining machine and complete after-sales service. If you are interested in investing in a crude vegetable oil refining project, please call us for machine customized service and detailed processing solutions.